Road Update – August 12, 2024 @ 8:00PM
As of 8:00pm: Due to the recent rainfall Division 10 in the Kindersley RM is reduced to 10-ton.
No mud is to be brought up from lease areas.
If you have questions, call bylaw at 306-460-8056
As of 8:00pm: Due to the recent rainfall Division 10 in the Kindersley RM is reduced to 10-ton.
No mud is to be brought up from lease areas.
If you have questions, call bylaw at 306-460-8056
Kindersley RM Division 9 will re-open to primary weight at 12:00 noon today.
All other Kindersley RM Divisions continue to be open to primary weight.
No mud is to be brought up from lease areas.
If you have questions call bylaw at (306) 460-8056.
As of 4:00pm: Due to the recent rainfall Divisions 9 in the Kindersley RM are reduced to 10-ton.
No rig moves are allowed in these Divisions until further notice.
No mud is to be brought up from lease areas.
If you have questions, please call bylaw at (306) 460-8056.
As of 8:30am: All RM of Kindersley Divisions are open to primary weight.
No mud is to be brought up from lease areas.
If you have questions, call bylaw at (306) 460-8056
As of 9:30am: RM of Kindersley Divisions 1, 2, 3, 4, 5, 6, 7, 8, & 9 are open to primary weight
Division 10 continues to be restricted at 10-ton – No rig moves in this area until further notice
No mud is to be brought up from lease areas.
If you have questions, please call bylaw at (306) 460-8056
As of 9:30pm: Due to the recent rainfall Divisions 1, 2, 3, 4, 5, 6, & 10 in the Kindersley RM are reduced to 10-ton.
No rig moves are allowed in these Divisions until further notice.
No mud is to be brought up from lease areas.
If you have questions, please call bylaw at (306) 460-8056.
All divisions in the RM of Kindersley #290 are open to primary weight.
There maybe some detours so be careful. No mud from lease areas is to be brought up onto the grid roads.
If you have questions, please contact Bylaw at (306) 460-8056.
As of noon tomorrow, July 3rd all Divisions in the RM of Kindersley #290 will open to primary weight.
In Divisions 1, 2, 3 & 6 drilling, frac and service rig moves will be allowed. Divisions 4, 5, 7, 8, 9 & 10 will remain closed to all rig moves for the time being.
No mud is to be brought up onto the grid roads.
If you have questions, please call Bylaw at (306) 460-8056.
All roads in the RM of Kindersley are at secondary weight except in Division 10 the 302 west of Hartwell Rd remains at 8 ton.
There are no drilling, frac or service rigs moves allowed at this time.
If you have questions, please call Bylaw at 306-460-8056.
Due to extreme wet conditions, the RM of Kindersley is limited to 8-ton road restriction until future notice.
Division 10 – Drive with extreme caution as there are roads washed out that you may not see in advance.
Division 3 – Road 290 from highway 21 east to the Beadle Grid is now closed.
If you have questions, please call Bylaw at (306) 460-8056.